PROJ 592 Week 5 Assignment Problems

5-1 Earned Value Calculation

You are 4 months into a 6 month project. The project is linear, which means that the progress and spending occurs at a constant rate. Our crack project team of highly skilled associates has worked diligently and put in extra hours to keep the project going.  Our accounting department has provided the following data at the end of month 4:

Actual cost to date = $88,800

Planned expenditures to date = $101,000

The CFO is excited and has sent you an email congratulating you for being 12.07% under budget. However, is it really time to hold a team celebration? That would be fun but your project manager mentality kicks in. Those numbers look good but how are we ‘really’ doing? To understand the true project performance, we need to apply earned value techniques.

The missing piece we need is Earned Value (i.e. what we have actually accomplished so far). You meet with your team and find that only 6 of the 7 tasks scheduled to be complete by the end of month 4 have actually been completed. Task 7 isn’t even started! This information gives you the final data you need to apply ‘Earned Value’ and develop an objective analysis.

What are the PV, EV, and AC for the project at the end of month 4?
What are the SV, CV, SPI, and CPI for the project?
Assess the project performance to date? Do you get to have the celebration?

Hi there! Get instant help with . Without paying anything upfront.

 

5-2 Earned Value Calculation

                                                                                                                            

Project Schedule and Budget Data Provided:

TaskDuration (days)Predecessor(s)Budget
A2$1,600
B5$4,000
C3A$14,050
D4B$5,800
E6B$12,000
F4C,D$5,200
G3E$3,900
 Project Totals:$46,550

 

Status of the project at the end of day 6:                                                                

Task% CompleteActual Cost of Work Performed
A100%$1,800
B100%$4,500
C90%$13,500
D10%$500
E0%$0
F0%$0
G0%$0

 

 

Project Network Diagram                                                                                                                               

 

 

 

Tasks                          Duration (Days)

AAA             
                
BBBBBB          
                
C  CCC          
                
D     DDDD      
                
E     EEEEEE    
                
F         FFFF  
                
G           GGG 
                
012345678910111213141516

 

 

  1. Calculate the schedule variance for each task and the total project.

 

 

  1. Calculate the cost variance for each task and the total project.

 

     

  1. What is your assessment of the project at this time?

 

 

 

 